
H2 Wind Project Update: April 1, 2025
On March 27, the Alberta Utilities Commission (AUC) responded to Capital Power’s March 11th update letter which included a third-party incident report on the T33 incident. The AUC outlined a process to lift the suspension order and authorize Capital Power to resume construction of the Halkirk 2 Wind Power Project. The process includes Capital Power registering a new proceeding by filing an application to have the suspension order lifted, including refiling its update letter and third-party incident report. On receipt of the application, the AUC will establish a process to consider the application.
The cleanup and removal of large debris at T33 is nearing completion. In early April (pending snow cover), crews will complete a sweep of the area and pick up any small debris and fiberglass shards from the damaged blades. Environmental remediation for T33 will begin in early April, which includes the removal and disposal of any contaminated soil and replacement with new soil.
An assessment of the tower will be completed in mid-to late April to finalize the disassembly plan of the five tower sections. Once complete, the concrete foundation will be inspected to ensure it was not damaged when the nacelle and rotor detached and fell to the ground. Pending the outcome of the foundation assessment and AUC approval, we expect to reconstruct T33 in June 2025. Upon completion, the project will have 28 wind turbines for a total installed generation capacity of 126 MW.
We will share more information about the plan to rebuild T33 following the AUC’s direction and the result of the foundation inspection.
Please contact us anytime.
1-855-703-5005 (toll free)
projects@capitalpower.com
The Halkirk 2 Wind Project Team