Castor North

CASTOR NORTH SOLAR PROJECT

Project Name: Castor North Solar Project
Project Location: North of Castor east side of Hwy 36
North of TR384 south of creek
10 quarters in 38-13: 32, 33, 27, 28
Developer: Sky Sustainable and Green Energy Corp
Consultant - CanWest Solar
Developer Contact: Jim Scantland - CanWest Solar
jim@canwestsolar.com
250-878-1003
Project Capacity: Approx. 250 MW on 10 quarters
Project Status at Present: Actual foot print of land used submitted to County
Second project behind the Castor West
No open house or public engagement yet
No prelim designs done that have been shared